Short answer
Most residential lining jobs are done in one day and most bursting jobs in one to two, after a separate inspection and permit lead time of a few days to a couple of weeks. The water is off for a few hours on the day. Access is usually a cleanout or one or two small pits, which can leave most of the yard undisturbed; access and restoration depend on the project. A final camera pass and the permit inspection close the job.
Before the day
- Inspection and trace — about an hour. The camera video with distances and the surface marks are the basis for everything after.
- Proposal — written from the footage: which method, from where to where, what is being spot-repaired, and the written paperwork for your job.
- Permit — a side sewer permit from Seattle Public Utilities for yard work in Seattle, or the equivalent in the suburbs. Lead time varies from days to a couple of weeks; the permit guide explains the process.
- Utility locates — public utilities are marked before any pit is dug.
- Scheduling — with weather in mind. Lining can go ahead in rain; bursting pits in saturated ground are slower and messier.
Lining day
| Time | What is happening | What it means for you |
|---|---|---|
| Morning | Jetting, root cutting, grinding offsets, pre-lining video | Water off from here |
| Midday | Liner pulled in and inflated; UV light train cures it section by section | Quiet; a small generator and control unit outside |
| Early afternoon | Ends trimmed, branch connections reinstated, post-lining video | Water back on |
| Afterward | Permit inspection; written paperwork for your job | Access and restoration depend on the project; your written scope spells out what to expect |
A run that needs a small spot repair first adds a half-day to a day, usually done ahead of the lining so the liner goes through a continuous host.
Bursting day(s)
- Pits — one at the house end, one near the property line or the main. A few feet square, dug to pipe depth. Deep street ends take longer.
- Cable through the old pipe from pit to pit.
- Fusing the new HDPE pipe into a single length above ground.
- The pull — the bursting head and new pipe are winched through. Minutes to an hour depending on length and soil.
- Connections at each end; inspection; backfill and compaction; surface restored.
One long day is typical; two when the street-end pit is deep or the connection at the main needs work. Water is off for the pull and the connections, usually a few hours.
What the yard looks like after
Lining from a cleanout usually works from small access points, which can leave most of the yard undisturbed. Bursting needs a pit at each end, and a spot repair needs one at the damaged section. Access and restoration depend on the project, and your written scope spells out what to expect.
What can extend it
- The line needs more preparation than the first camera showed — heavy scale, a second offset.
- Saturated ground after days of rain, for anything involving a pit.
- A shared side sewer that turns out to serve a neighbor, which changes the permit and the agreement.
- A failed connection at the main that needs the street end opened, sometimes with a right-of-way permit.
None of these are unusual, and all of them are visible early if the inspection was thorough. Our trenchless page covers the methods; this timeline is what they look like from the kitchen window.
Questions people also ask
Do I need to be home?
For the start and the finish, ideally — to confirm access and to see the final video. During the work you can be out, as long as nobody in the house uses water while the line is open.
Can I use the toilet during the job?
Not while the line is being lined or burst. Plan for a few hours without water. For a longer job the crew can tell you when there will be a window.
What about my landscaping?
Lining from a cleanout usually works from small access points, which can leave most of the yard undisturbed. Bursting needs a pit at each end, typically a few feet square. Access and restoration depend on the project, and your written scope spells out what to expect.
What holds things up?
Permit lead time, weather that saturates the ground, a line that needs more cleaning or a spot repair than expected, and a shared line that needs a neighbor's sign-off.
More of the questions we hear every week are on the FAQ page .
Sources
If this is your problem
Trenchless sewer repair
The service page — what we do, how we decide, and what you get in writing.
OpenOr just ask us
(425) 478-3133Open 24/7/365. Estimates and second opinions are free — see our current offers .